为研究简支转连续体系梁桥的墩顶负弯矩区力学性能,以墩顶支点处转角连续为变形协调条件,采用双线性法和龄期调整有效弹性模量法推导墩顶负弯矩区约束弯矩的解析表达式,将约束弯矩的理论结果与试验结果及美国波特兰水泥协会法、施工技术实验室法的计算结果进行对比。研究结果表明:简支转连续过程中,预应力筋张拉对墩顶负弯矩区影响最大;本文提出的墩顶负弯矩计算方法得到的约束弯矩与试验实测结果及其他两种计算方法的结果基本吻合,表明本文所提方法的精确性较好,能初步估算墩顶负弯矩区是否存在开裂的风险。
Abstract:To investigate the mechanical properties of the negative bending moment zone(NBMZ) at the pier top of a simply supported to continuous girder, the deformation coordination condition is taken as the continuous rotation angle at the pier top fulcrum. The analytical expression of the restraint bending moment in the NBMZ at the pier top is derived using bilinear method(BM) and age-adjusted effective modulus(AAEM) method. Theoretical analysis are carried out. The results of the proposed method are compared with that of the field experiments and Portland Cement Association(PCA) method and Construction Technology Laboratories(CTL) method. The research results indicate that the tensioning of prestressed reinforcement has the greatest impact on the negative bending moment zone at the pier top during the process of simple supported to continuous girder; The values of the proposed method are in good agreement with the measured experimental values and PCA method and CTL method. This indicates the proposed method BM-AAEM has the high accuracy, which can preliminarily estimate whether there is a risk of cracking in the NBMZ at the top of the pier.
[1] MA Z J,HUO X M,TADROS M K,et al.Restraint moments in precast/prestressed concrete continuous bridges[J].PCI Journal,1998,43(6):40-57.
[2] PETERMAN R J,RAMIREZ J A.Restraint moments in bridges with full-span prestressed concrete form panels[J].PCI Journal,1998,43(1):54-73.
[3] MENKULASI F,PATEL A,BAGHI H.An investigation of AASHTO′s requirements for providing continuity in simple span bridges made continuous[J].Engineering Structures,2018,158:175-198.
[4] AZIZINAMINI A.Simple for dead load:continuous for live load steel bridge systems[J].Engineering Journal,2014,51(2):59-82.
[5] LAMPE N,MOSSAHEBI N,YAKEL A,et al.Development and experimental testing of connections for the simple for dead load:continuous for live load steel bridge system[J].Engineering Journal,2014,51(2):83-108.
[6] FARIMANI R,JAVIDI S,KOWALSKI D,et al.Numerical analysis and design provision development for the simple for dead load:continuous for live load steel bridge system[J].Engineering Journal,2014,51(2):109-126.
[7] YAKEL A,AZIZINAMINI A.Field application case studies and long-term monitoring of bridges utilizing the simple for dead:continuous for live bridge system[J].Engineering Journal,2014,51(3):155-176.
[8] JAVIDI S,YAKEL A,AZIZINAMINI A.Experimental investigation,application and monitoring of a simple for dead load:continuous for live load connection for accelerated modular steel bridge construction[J].Engineering Journal,2014 ,51(3):177-198.
[9] TAGHINEZHADBILONDY R,YAKEL A,AZIZINAMINI A.Deck-pier connection detail for the simple for dead load and continuous for live load bridge system in seismic regions[J].Engineering Structures,2018,173:76-88.
[10] ABBIATI G,CAZZADOR E,ALESSANDRI S,et al.Experimental characterization and component-based modeling of deck-to-pier connections for composite bridges[J].Journal of Constructional Steel Research,2018,150:31-50.
[11] XU D,ZHANG Y,XU F Y,et al.Unified flexural design method for deep and shallow beams using non-linear grid model[J].Structural Engineering International,2017,27(4):482-491.
[12] ZHANG Y,XU D,LIU C.Behavior and stress check of concrete box girders strengthened by external prestressing[J].Computers and Concrete,2018,22(2):133-142.
[13] ZHANG Y,XU D.Application of the corresponding force matrix in analysis and reinforcement design of concrete box bridges[J].Structural Engineering International,2022,32(2):175-182.
[14] MOTWANI P,RATHER A I,LASKAR A.Transfer stage parameters for concrete beams prestressed with BFRP bars:experimental and finite element studies[J].Construction and Building Materials,2022,315:125639.
[15] KYT??L?? U,TULONEN J,ASP O,et al.Experimental study of moment redistribution before yielding in precast prestressed concrete beams made continuous[J].Structural Concrete,2023,24(6):6933-6952.
[16] 成子满.简支转连续钢-混组合梁负弯矩区连接构造受力性能试验研究[J].建筑结构,2024,54(1):34-40.
[17] 王荣霞,陈中宇,万田宝,等.简支转连续钢-混组合梁桥负弯矩区设计及工程应用[J].建筑结构,2024,54(1):41-46.
[18] BA??ANT Z.Prediction of concrete creep effects using age-adjusted effective modulus method[J].Journal of the American Concrete Institute,1972,69:212-217.
[19] ZHANG Z J,LIU Y J,ZHANG T T,et al.Long-term behavior of the steel-concrete composite girder bridge with old and new concrete[J].Structures,2024,70:107887.
[20] FIB.CEB-FIP model code 2010[S].Lausanne,Switzerland:Thomas Thelford,2010.
[21] ACI.ACI 209 R-29:prediction of creep,shrinkage and temperature effects in concrete structures[R].Detroit,USA:American Concrete Institute,1992.